Story Point accounting – I am on the fence on this one folks...or am I?
Firstly, I'd like to say thanks to everyone for the wonderful comments received in regards my writing. Frankly, I am flattered. I'd also like to apologize again for not writing more regularly. It seems like I just never get the time these days with my busy life.
The scenario I want to specifically talk about today is as follows:
You plan a Story into a sprint, let’s say an 8 point Story, but the team doesn’t get to finish the Story. How should you account for the Story Points in the current and subsequent Sprints? Let’s just say for explanation's sake that the remaining work for the subsequent Sprint is 3 points.
Well, almost all if not all the Agile thought leaders agree that the team should not claim any points in the current Sprint. So even if the team completed 5 points worth of the Story, because it’s incomplete, the Team adds 0 points to their velocity for the current Sprint. I agree with this.
But here’s where it gets interesting. And there are definitely 2 opinions on this.
In the subsequent Sprint, do you claim all the Story Points originally assigned to the Story (8 in this example) or do you just claim 3 points?
Let me first explain why I like the first option.
Claiming all the Story Points in the subsequent Sprint is good because you actually did all the work and so from a pure “value” perspective (Value delivered toward the overall Product), this is the most accurate.
If you choose to only accept 3 points however, your average velocity actually drops lower than your true velocity. Moreover, the reason why you didn’t complete the story in the first place is because it was probably even bigger than the original estimated size –- that’s why you couldn’t finish it in the first Sprint. So if you only claim 3 points in the subsequent Sprint, you’re actually dropping your real velocity even more than just the 5 original points.
The benefit of only planning for and accepting 3 points in the subsequent Sprint is that it is the most realistic representation of the remaining effort. So your planning for the subsequent Sprint will be more accurate with a more predictable outcome I would think. Additionally, it’s a more conservative way of accounting your velocity. If you think about it, we humans are generally optimistic with our estimates in the first place so going the conservative route I think is not such a bad thing.
I posted this question to the Scrum Development forum. And interestingly, folks were divided in their opinions on how to do this. I think it was Ron Jefferies that suggested that Teams try whichever they think is best.
Personally, I think if you look at the problem from a pure Value perspective, then I think the first option is best, i.e., claim all the points in the subsequent Sprint.
If you value ongoing planning and predictability more, then I think the second option is best as you can plan more realistically based on the actual remaining effort.
Let me know what you think.
Happy sprinting
Jack